Investment: Development of the BorsodChem industrial power plant, long-term operation and maintenance of the power plant

Customer: BC Erőmű Kft.

Investment amount: EUR 44 million

Project implementation period: 2000–2001

Project implementation site: Kazincbarcika, BorsodChem Zrt.


In 1999 BorsodChem Zrt, a leading chemical company in Central Europe, founded BC-Erőmű Kft. in collaboration with ÉMÁSZ Nyrt. and MOL Nyrt. to build a high-performance industrial power plant in order to cover its increasing power and steam demand at affordable energy costs.

Sinergy Kft. (which is part of ALTEO since May 2015), participated in the development of the investment project. ALTEO currently conducts the operation and maintenance of the power plant based on a long-term contract. The power plant consists of two gas turbines and two co-fired heat recovery steam boilers. The gas turbines and the recovery boilers are fired exclusively with natural gas. If the gas turbines stop, two backup boilers will provide the required amount of steam.

bc-960×660
FacebookTwitterLinkedIn